COSTING FOR A SPINNING MILL

INTTRODUCTION:

It is better to review the basics concepts, costing  methods and techniques and elements of costing before we work out a costing for a spinning mill.

Cost accounting is a system of determining the costs of products or services. It has primarily developed to meet the needs of management.  It provides detailed cost information to various levels of management for efficient performance of their functions.

Financial accounting provides information about profit , loss, cost etc., of the collective activities of the business as a whole. It does not give the data regarding costs by departments, products, processes and sales territories etc. Financial accounting does not fully analyse the losses due to idle time, idle plant capacity, inefficient labour, sub-standard materials, etc. Cost accounting is not restricted to past. It is concerned with the ascertainment of past, present and expected future costs of products manufactured or services supplied. Cost accounting provides detailed cost information to various levels of management for efficient performance of their functions.

"A cost  is the value of economic resources used as a result of producing or doing the things costed"

Cost is ascertained by cost centres or  cost units or by both.

For the purpose of ascertaining cost, the whole organisation is divided into small parts of sections. Each small section is treated as a cost centre of which cost is ascertained.   A cost centre is defined as " a location, person, or item of equipment(or group of these) for which costs may be ascertained and used for the purpose of control.  A cost accountant sets up cost centres to enable him to ascertain the costs he needs to know. A cost centre is charged with all the costs that relate to it. The purpose of ascertaining the cost of  cost centre is cost control.  The person in charge of a cost centre is held responsible for the control of cost of that centre.

Cost unit  breaks up the cost into smaller sub-divisions and helps in ascertaining the cost of saleable products or services. A cost unit is defined as a " unit of product , service or time in relation to which cost may be ascertained or expressed."   For example in a spinning mill the cost per kg of yarn may be ascertained. Kg of yarn is cost unit.  In short  Cost unit is unit of measurement of cost.

 

METHODS  OF COSTING:

Method of  costing refers to the techniques and processes employed in the ascertainment of costs. The method of costing to be applied in a particular concern depends upon the type and nature of manufacturing activity.   Basically there are two methods of costing

1.Job costing:   Cost unit in job order costing is taken to be a job or work order for which costs are separetely collected and computed.

2.Process costing:  This is used in mass production industries manufacturing standardised products in continuous processes of manufacutring. Cost are accumulated for each process or department. For spinning mills , process costing  is employed.

 

TECHNIQUES OF COSTING:

These techniques  may be used for special pupose of control and policy in any business irrespective of the method of costing being used there.

Standard costing:  This is the valuable technique to control the cost. In this technique, standard cost is predetermined as target of performance and actual performance is measured against the standard.  The difference between standard and actual costs are analysed to know teh reasons for the difference so that corrective actions may be taken.

Marginal costing: In this technique, cost is divided into fixed and variable and the variable is of special interest and importance. This is because, marginal costing regards only variable costs as the costs of products.  Fixed cost is treated as period cost and no attempt is made to allocate or apportion this cost to individual cost centres   or cost units.

 

Cost Ascertainment is concerned with computation of actual costs. Ascertainment of actual costs reveals unprofitable activities  losses and inefficiencies  .

Cost Estimation  is the process of predetermining costs of goods or services. The costs are determined in advance of production and precede the operations. Estimated costs are definitely the future costs and are based on teh average of the past  actual costs adjusted for future anticipated changes in future. Cost estimates are used in the preparation of the budgets. It helps in evaulating performance. It is used in preparing projected financial statements. Cost estimates may serve as targets in controlling   the costs.

 

CLASSIFICATION OF COSTS:

Costs are classified into direct costs and  indirect costs on the basis of their identifiability with cost units or processesses or cost centres.

DIRECT COST: These are the costs which are incurred for and conveniently indentified with a particular cost unit, process or equipment. For a spinning mill, costs of rawmaterial used, packing material, freight etc are direct costs

INDIRECT COST: These are general costs and are incurred for the benefit of  a number of cost units, processes or departments. These costs cannot be conveniently identified with a particular cost unit or cost centre. In a spining mill, power cost, administrative wages, managerial salaries, materials used in repairs etc are indirect costs.

The terms direct and indirect should be used in relation to the object of costing. An item of cost may be direct cost in one case and the same may be indirect in the other case.It is the nature of business and the cost unit chosen  that  will determine whether a particular cost is direct or indirect.

 

FIXED AND VARIABLE COSTS; Costs behave differently when level of production rises or falls. Certain costs change in sympathy with production level while other costs remain unchanged. As such on the basis of behaviour or variability, costs are classifed into fixed, variable and sem-variable.

FIXEDCOSTS; These costs remain constant in "total" amount over a wide range of activity for a specified period of time. They do  not increase or decrease when the volume of production changes.

VARIABLE COSTS: These costs tend to vary in direct proportion to the volume of  output. In other words, when volume of output increases, total variable cost also increases and vice-versa.

 

ELEMENTS OF COST: A cost is composed of three elements i.e. material , labour and expense. Each of these elements  may be direct or indirect.

DIRECT COST INDIRECT COST
Direct material Indirect material
Direct labour Indirect labour
Direct expenses Indirect expenses

 

MATERIAL COST: 

DIRECT MATERIAL  is that which can be conveniently identified with and allocated to cost units. Direct materials generally become a part of the finished product. For example, cotton used  in a spinning mill is a direct material.

INDIRECT MATERIAL is that   which can not  be conveniently identified with individual cost units.  In a spinning mill, engineering department spares, maintenance spares, lubricating oils, greases, ring travellers etc

LABOUR COST:

DIRECT LABOUR cost consists of wages paid to workers directly engaged in converting  raw materials into finished products. These wages can be conveniently identified with a particular product, job or process.

INDIRECT LABOUR is of general character and cannot be conveniently identified with a  particular cost unit. In other words, indirect labour is not directly engaged in the production operations but only to assist or help in proudciton operations.  For example in a spinning mill, the number of maintenance workers, no of  workers in utility department etc

 

EXPENSES; All costs other than material and labour are termed as expenses.

DIRECT EXPENSES are those expenses which are specifically incurred in connection with a particular job or cost unit. Direct expenses are also known as chargeable expenses.

INDIRECT EXPENSES can not be directly identified with a  particular job, process and are common to cost units and cost centres.

 

PRIME COST = Direct material +Direct labour + Direct  expenses

OVERHEAD = Indirect material + Indirect labour + Indirect expenses

TOTAL COST = PRIME COST + OVERHEAD

 

ADVANTAGES OF COST ACCOUNTING:

 

ESSENTIALS OF A GOOD COST ACCOUNTING SYSTEM:

 

CASE 1.  Project costing for a    POLY/COTTON  PLANT with autodoffing and link to autoconer:(IN INDONESIA)

Following information is required to work out a costing for a new plant:

Let us  work out a project cost:

For this , i have used the details of   the modern mill which is running in Indonesia from  year 2000

STEP NO.1: Contribution to be calculated.  In general for a spinning mill ,contribution per kg  ofa particular count is calculated    to work out the economics for a new project as well as for a running   mill.

Cotribution = selling price - direct cost

Direct cost for a spinning mill includes  rawmaterial price, packing cost, freight.  All other costs are either fixed costs or semi variable costs. The other costs can not be conveniently allocated to per kg of a particular count.

The basic idea of a new project or a running plant  is to maximise this contribution. Because once the plant is designed, spares cost, power cost, administration cost,labour cost etc almost remain constant. There will not be significant changes in these costs  for different count patterns if  the plant is utilisation is same.

The following table gives the details of count pattern, selling price, rawmaterial price, packing cost and contribution per kg of different counts for a particular period ( year 2000). This is just an example , one should understand that the selling price, rawmaterial price and all other costs keep changing.  THis is the reason why costing is important for a running mill.  All the costs are changing. Some costs change every month, some  once in a year.   Therefore costing plays a major role to run the plant efficiently.

count no. of spls no of mcs prdn/mc prdn kgs/day  raw material cost/kg packing cost /kg freight per kg commn 2% on selling price selling price / kg contribn per kg
20s CVC 4480 4 1109 4436 1.456 0.046 0.051 0.04 2.2 2674
24s CVC 4480 4 881 3525 1.456 0.046 0.051 0.05 2.3 2470
30s CVC 5600 5 679 3394 1.456 0.046 0.051 0.05 2.4 2712
30s TC 4480 4 679 2716 1.240 0.046 0.051 0.04 2.15 2091
36s TC 6720 6 552 3315 1.240 0.046 0.051 0.05 2.4 3365
    23   17385       contrbn/ day 13312

In the above table, all the costs are in US$. The ringframes are with 1120 spindles per machine with automatic doffing and link to autoconer. Packing cost is based on indonesian packing material prices for carton packing.

 

The ultimate aim of the project is to maximise the contribution.  Looking into the cotribution per kg of yarn, the project should produce only 36s TC. But in this project they have considered 5 different counts. Because

 

STEP NO. 2: To work out the Total Investment cost ( machineries, accessories, land and builidng, humdification and electrical instruments)

The following table gives the requirement of produciton  machines. To calculate the number of back proess and winding drums  required, a detailed spin plan should be worked out with  speeds and efficiencies to be achieved in each machine.

While calculating the no of   machines required, m/c utilisation, m/c efficiency , waste percentage, twist multipliers, delivery speeds etc  should be considered properly.  These factors should be decided based on yarn quality required, end breakge rates and the capacity of machine.

INVESTMENT ON MACHINERY

MACHINERY NO. OF MCS RATE / MC TOTAL COST
Trutzschler Blowrrom line for cotton 1  line 416,640 416,640
Trutschler Blowrrom line for Polyester 1 Line 321,365 321,365
Trutshcler DK-903 cards 22 92,500 2,035,000
Rieter RSB-D30 draw frames (with autoleveller) 6   1,648,000
Rieter double delivery drawframe 10
Rieter unilap 2
Rieter E62 combers 10
Howa speed frames with overhead blower 7 144530 1,011,710
Ring frames with autodoffer 23 148,960 3,426,080
winding machines ( 26 drums per mc) 23 93,200 2,143,600
Roving transport ( manual) 1 150,000 150,000
Argus fire system 1 50,000 50,000
       
    TOTAL 11,202,395

Some of the following points can be considered while deciding the machines.

From the above table it is clear that, 23 ringframes with 1120 spindles are working with auto doffing and with link to autoconer. The major advantage of this automation is to reduce labour and to reduce the problems related to material handling. One has to really work out the benefits achieved because of this and the pay back for the extra investment. 

Drawframe contributes a lot to the yarn quality and the ringframe and winding machine working. It is always better to go in for the best drawframes like RSB-D30 drawframes with autoleveller. It is not wise to buy  a cheaper drawframe and save money.

It is always better to keep excess carding and autoleveller drawframes, so that flexibility of the project is also maintained. If the coarser counts contributes more and the market is good, overall production can be increased. If the market is for finer count, both the machines (carding and drawframes)can be run at slower speeds, which will surely contribute to yarn quality.

Speeds of speedframe , combers and ringframes do not affect the yarn quality as it is affected by card and drawframe speeds.

Blow room capacity should be utilised to the maximum, as it consumes a lot of power ,space and money.

Ringframe specification should be perfect, because the working performance and power consumption of the ringframe depends on the specifications like, lift, ring dia, no of spindles etc. Ring frame specification should be decided   to get the maximum production per spindle and to reduce the power consumed   per kg of yarn produced by that spindle. Because the investment cost and the power consumption for the  ringframe is the highest in a spinning mill.

 

INVESTMENT ON ACCESSORIES:

The following table gives the details of  the accessories like cans for carding, drawframe, bobbins, trollies etc

ACCESSORIES NO. OF MCS RATE / MC TOTAL COST
Carding cans  36" x 48" 120 160 19,200
comber cans 24" x 48" 350 85 29750
Drawframe cans 20" x 48" 1100 53 58,300
Identification bands 20" 400 1.2 480
Identification bands 24" 50 1.8 90
Roving and spinning bobbins     36,000
Plastic crates 400 6 2,400
trolleys     10,000
Cone trolly 80 200 16,000
Fork lift 1 27,000 27,000
hand truck 3 1000 3,000
       
    TOTAL 202,220

 

SERVICE AND MAINTENANCE EQUIPMENTS:

The following table gives the details about  the investments required on service and maintenance  equipments

SERVICE AND MAINTENANCE EQUIPEMENTS NO OF MCS RATE/MC TOTAL PRICE
Cots buffing machine and accessories 1 20000 20000
Card room accessories 1 set 60,000 60,000
Spindle oil lubricator 1 4000 4000
Clearer roller cleaning machine 1 3000 3000
Vacuum cleaner 5 3000 15000
pneumatic cleaners 6 500 3000
Weighing balance 3 2000 6000
Strapping machine 2 2000 4000
Premier autosorter 1 2500 2500
Premier uster tester 1 45000 45000
Premier strength tester 1 45000 45000
premier fiber testing 1 45000 45000
Premier Classidata 1 25000 25000
Erection charges     150000
    TOTAL 427500

Card service machines like   Flat tops clipping machine and flats grinding machine are very important for yarn quality. One should not look for cheaper machine. It is always better to go for reputed manufacturers like  GRAF, HOLLINGSWORTH etc.

Rubber cots contributes a lot to yarn quality. Bad buffing in ring frame can increase the imperfections by 15%.  Poor quality of buffing in drawframe and speedframes can affect both production and quality. It is better to go for the best cots mounting machine and cots buffing machine.

 

HUMIDIFICATION AND ELECTRICAL EQUIPMENTS:

The following table gives the details about the investments required on  humdification and electrical istruments

Electrical installation including transformer, incoming and outgoing panels, bus duct, capacitor, etc for 3800 KVA 350,000
Cables 125,000
Compressor, Dryer and pipe lines 180,000
humidifaction system 767,000
chillers 176,000
Ducting and installation for humidification system 125,000
workshops, hydrant and other equipments 100,000
   

TOTAL

1,823,000

In indonesia, most of the units use PLN power and some of the spinning mills use Gensets. A detailed costing has to be done to compare the cost per unit  to decide, Whether to use the PLN power or to go in for Gensets. while working out the costing  finance cost on investment , overhauling cost, running cost, efficiency of the machine  should be considered for cost caluculation in the case of Genset. In case of PLN power, the losses due to power interruption( based on the area data), finance cost on initial investment,   md charges, unit charges to be considered. It is  better to use 50% PLN and 50 % own generation.

 

 

The following table gives the details about land and builiding investments

Land cost 200,000
Land development 40,000
Factory building Including Service ally 192 x 62 meters

11,712 Square meter @ 120 usd/sq meter

1,405,440
Road and others 40,000

TOTAL

1,445,440

 

STEP NO.3: To calculate the expenses ( labour, power, stores,working capital, insurance etc)

Working capital = 3,000,000     

LABOUR:The following table gives the details about   labour requirement

DEPARTMENT No of people required
Production 140
packing 15
maintenance 30
utility 17
administration and personal dept 20
   

Total no of people required per day

222

 

wages at 50 usd/month including bonus and insurance 111,00
other facilities at 35 % 3,885
salaries for managerial staff 10000
Other facilities at 35 % 3500
   

Total labour cost / month

28485

POWER: The following table gives the details about the power

Total units(KWH) produced (consumed)per day 69559
Unit cost (cost / KWH) 0.03
Total production in Kgs 17,390
KWH/ Kg of yarn 4.0
TOTAL POWER COST /DAY 2087

SPARES:The following table shows the spares cost, repair , and insurance

spares cost at usd 8/1000 spindle shift 222,566
repairs and other overheads 200,000
Insurance at 0.175% on investment and working capital 31320
TOTAL cost per year 453886

 

 

STEP NO.4: PAY BACK CALCULATION

DETAILS IN USD
INVESTMENT:  
Land and building 1,444,440
Machinery, accessories & service equipments 11,832,115
Electrical and Humidification ducts 1,823,000
   

TOTAL INVESTMENT

15,099,555
   
WORKING CAPITAL 3,000,000

GRAND TOTAL

18,099,555
   
RECURRING EXPENDITURES PER DAY  
Salaries and Wages 949.5
Power cost 2087
Stores , repairs and insurance 1260.8

TOTAL

4297.3
   
INTEREST CALCULATION (per day)  
On capital 8% 3355.5
on working capital 9% 750
   
TOTAL EXPENSES INCLUDING INTEREST 8402.8
   
TOTAL CONTRIBUTION PER DAY 13312
NET PROFIT( before depreciation & taxation) 4909.2
PAY BACK PERIOD 8.54 years